Automate and standardize multi-story building schedules through repetitive spatiotemporal model |
Tartalom: | http://hdl.handle.net/10890/51315 |
---|---|
Archívum: | Műegyetem Digitális Archívum |
Gyűjtemény: |
1. Tudományos közlemények, publikációk
Konferenciák gyűjteményei Creative Construction Conference Creative Construction Conference, 2023 |
Cím: |
Automate and standardize multi-story building schedules through repetitive spatiotemporal model
|
Létrehozó: |
Francis, Adel
|
Kiadó: |
Budapest University of Technology and Economics
|
Dátum: |
2023-08-03T09:09:58Z
2023-08-03T09:09:58Z
2023
|
Tartalmi leírás: |
Traditional planning models, based on Gantt-Precedence logic, focus on defining activities and
establishing their constraints. Resources can then be assigned to those activities. Spatial constraints
are usually neglected, resulting in site congestion or relaxation. This is due to the lack of representation
of the sequence of work and supply flows on the site. Spatiotemporal models are considered more
appropriate, especially for planning the construction of buildings projects. These models simultaneously
consider activities, resources, and space as constraints to construct a realistic execution schedule. In
addition, multi-story buildings share many common components and activities. Thus, it is plausible to
think of establishing standardization in order to create an automated system to support the construction
of validated schedules. The objective of this study is to develop an automated and standardized
approach for creating construction schedules for multi-story buildings. Using the data from many studies,
a mapping of multi-story construction schedules through repetitive spatiotemporal approaches can be
created to allow for a consistent and systematic representation of the schedule.
|